Home / Economy / 17 Million Tender Announced for Kutaisi Airport Expansion Works

17 Million Tender Announced for Kutaisi Airport Expansion Works

Kutaisi airport expansion works to switch to a new phase.

A new 16.9 million tender was announced for covering the green roof, stained glass and facade of the new terminal of the airport.

The winner company must complete the works within 24 weeks. Including completion of roofing works of the entire building in 18 weeks, so that the buyer can manage other works.

After the expansion of Kutaisi airport, there will be 2 halls. 1 main hall – is designed for departure passengers, for registration and the second will be arrival area.

At the airport, there will be a café-restaurant and “lounge” from where the passengers will be able to get on the roof of the amphitheater.

The company “Anagi” is currently implementing the construction of the new terminal of the airport under the 26.4 million contract.